CUTS>CITEE>7 Up Project> Project Progress Reports> Annexure E

ANNEXURE E

7-Up Project

Time Schedule (as on 2002.02.05)

February-July 2002

 

S.N

Activity

Responsibility

Date to Begin

Deadline

1.

Preface, Foreword and NRG discussions

Partners

2nd February 2002

10th February 2002

2.

Phase-I Country Reports (Edited)

Partners and CUTS

 

15th February 2002

3.

Phase-I Synthesis Report (Revised Draft)

Rakesh Basant

20th January 2002

15th February 2002

4.

Comments of PAC on the Synthesis Report

PAC and CUTS

16th February 2002

22nd February 2002

5.

Final Synthesis Report

Rakesh Basant

23rd February 2002

28th February 2002

6.

Analysis of Phase-II Questionnaires

Researchers

 

28th February 2002

7.

Synopsis of the Synthesis and Critical Analysis of Country Reports

Rakesh Basant

15th February 2002

7th March 2002

8.

Editing and Laying Out of Synthesis Report

CUTS

1st March 2002

7th March 2002

9.

Printing of Country and Synthesis Reports

CUTS

8th March 2002

15th March 2002

10.

Three Case Studies (Draft)

Partners and Researchers

15th January 2002

31st March 2002

11.

Comments of CUTS and PAC on the draft case studies

PAC and CUTS

1st April 2002

15th April

12.

Final Case Studies

Partners and Researchers

16th April 2002

30th April 2002

13.

Draft Country Report of Phase-II

Researchers

1st May 2002

10th May 2002

14.

Comments of PAC on Draft Phase-II Country Report

PAC and CUTS

11th May 2002

20th May 2002

15.

Draft Synthesis Report of Phase-II

Rakesh Basant

11th May 2002

25th May 2002

16.

Final Phase-II Country Reports

Researchers

21st May 2002

30th May 2002

17.

Comments of PAC on the Draft Phase-II Synthesis Report

PAC and CUTS

26th May 2002

10th June 2002

18.

Final Phase-II Synthesis Report

Rakesh Basant

11th June 2002

20th June 2002

19.

Phase-II Culmination Meeting in Geneva

CUTS

 

5-6th July 2002

 

CUTS>CITEE>7 Up Project> 6th Project Progress Reports> Annexure E

 